You work as a project manager for BlueWell Inc. You are currently working with the project stakeholders to identify risks in your project. You understand that the qualitative risk assessment and analysis can reflect the attitude of the project team and other stakeholders to risk. Effective assessment of risk requires management of the risk attitudes of the participants. What should you, the project manager, do with assessment of identified risks in consideration of the attitude and bias of the participants towards the project risk?
A) Document the bias for the risk events and communicate the bias with management
B) Evaluate and document the bias towards the risk events
C) Evaluate the bias through SWOT for true analysis of the risk events
D) Evaluate the bias towards the risk events and correct the assessment accordingly
Correct Answer:
Verified
Q225: Which of the following is a subset
Q226: You and your project team are identifying
Q227: In which of the following testing methodologies
Q228: Ben is the project manager of the
Q229: System Authorization is the risk management process.
Q231: Penetration testing (also called pen testing) is
Q232: You are the project manager of the
Q233: What course of action can be taken
Q234: You are the project manager for a
Q235: There are seven risks responses that a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents