Ben is the project manager of the YHT Project for his company. Alice, one of his team members, is confused about when project risks will happen in the project. Which one of the following statements is the most accurate about when project risk happens?
A) Project risk can happen at any moment.
B) Project risk is uncertain, so no one can predict when the event will happen.
C) Project risk happens throughout the project execution.
D) Project risk is always in the future.
Correct Answer:
Verified
Q223: Which of the following professionals is responsible
Q224: Neil works as a project manager for
Q225: Which of the following is a subset
Q226: You and your project team are identifying
Q227: In which of the following testing methodologies
Q229: System Authorization is the risk management process.
Q230: You work as a project manager for
Q231: Penetration testing (also called pen testing) is
Q232: You are the project manager of the
Q233: What course of action can be taken
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents