Question 266

Multiple Choice

You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the qualitative risk analysis process except for which one?


A) Risk management plan
B) Risk register
C) Stakeholder register
D) Project scope statement

Correct Answer: