Frank is the project manager of the NHH Project. He is working with the project team to create a plan to document the procedures to manage risks throughout the project. This document will define how risks will be identified and quantified. It will also define how contingency plans will be implemented by the project team. What document is Frank and the NHH Project team creating in this scenario?
A) Project management plan
B) Resource management plan
C) Risk management plan
D) Project plan
Correct Answer:
Verified
Q259: ISO 17799 has two parts. The first
Q260: According to U.S. Department of Defense (DoD)
Q261: An Authorizing Official plays the role of
Q262: Which of the following DITSCAP phases validates
Q263: Wendy is about to perform qualitative risk
Q265: You are the project manager of the
Q266: You work as a project manager for
Q267: Which of the following requires all general
Q268: Certification and Accreditation (C&A or CnA) is
Q269: Information risk management (IRM) is the process
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents