Joan is the project manager of the BTT project for her company. She has worked with her project to create risk responses for both positive and negative risk events within the project. As a result of this process Joan needs to update the project document updates. She has updated the assumptions log as a result of the findings and risk responses, but what other documentation will need to be updated as an output of risk response planning?
A) Lessons learned
B) Scope statement
C) Risk Breakdown Structure
D) Technical documentation
Correct Answer:
Verified
Q280: Mary is the project manager for the
Q281: Which of the following is NOT a
Q282: Numerous information security standards promote good security
Q283: Which of the following fields of management
Q284: Billy is the project manager of the
Q286: Which of the following is NOT considered
Q287: Information Security management is a process of
Q288: Which of the following documents is used
Q289: You are responsible for network and information
Q290: Which of the following describes residual risk
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents