Billy is the project manager of the HAR Project and is in month six of the project. The project is scheduled to last for 18 months. Management asks Billy how often the project team is participating in risk reassessment in this project. What should Billy tell management if he's following the best practices for risk management?
A) At every status meeting the project team project risk management is an agenda item.
B) Project risk management happens at every milestone.
C) Project risk management has been concluded with the project planning.
D) Project risk management is scheduled for every month in the 18-month project.
Correct Answer:
Verified
Q279: Which of the following are included in
Q280: Mary is the project manager for the
Q281: Which of the following is NOT a
Q282: Numerous information security standards promote good security
Q283: Which of the following fields of management
Q285: Joan is the project manager of the
Q286: Which of the following is NOT considered
Q287: Information Security management is a process of
Q288: Which of the following documents is used
Q289: You are responsible for network and information
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents