Question 311

Multiple Choice

Mark is the project manager of the BFL project for his organization. He and the project team are creating a probability and impact matrix using RAG rating. There is some confusion and disagreement among the project team as to how a certain risk is important and priority for attention should be managed. Where can Mark determine the priority of a risk given its probability and impact?


A) Risk response plan
B) Project sponsor
C) Risk management plan
D) Look-up table