____ Is a Method for Analyzing the Time Needed to Complete

Question 72

Multiple Choice

____ is a method for analyzing the time needed to complete each project task and identifying the minimum amount of time needed to complete the total project.


A) Just in Time (JIT)
B) Work Breakdown Structure (WBS)
C) Program Evaluation Review Technique (PERT)
D) Manufacturing Resource Planning (MRP)

Correct Answer: