A Project Team Submits an RFQ to Vendors When It

Question 75

Multiple Choice

A project team submits an RFQ to vendors when it knows all of the following EXCEPT ____.


A) make of the equipment needed
B) model of the equipment needed
C) titles of the software packages needed
D) price of the software needed

Correct Answer: