Matching
Four methods for estimating costs can be broadly identified:
-The PEP
A) where cost estimates are developed by comparing to past similar projects to provide outside view with the aim of reducing the variance
B) where estimates are established from preliminary engineering work with an accuracy range of approx.70 percentage points
C) which provides estimates based on the work during the Define stage with an accuracy range of approx.38 percentage points
D) usually used early in the life cycle when there is very limited information or time to prepare with an accuracy range of approx.90 percentage points
Correct Answer:
Verified
Q6: Matching
Earned Value Analysis takes into consideration three
Q7: Matching
We measure execution performance by comparing current
Q8: Matching
We measure execution performance by comparing current
Q9: Matching
We measure execution performance by comparing current
Q10: Graphical scheduling technique that acts as boundary
Q11: Budget estimation is a linear and completely
Q12: Matching
Four methods for estimating costs can be
Q13: Matching
Four methods for estimating costs can be
Q14: Matching
Four methods for estimating costs can be
Q16: Managing conformance is an iterative process that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents