Which one of the following statements best describes the critical path of a project network?
A) It is the sequence of activities between a project's start and finish that has the maximum amount of slack.
B) It is the sequence of activities that has the smallest normal activity cost.
C) It is the set of activities that has the smallest total number of predecessors.
D) It is the sequence of activities between a project's start and finish that takes the longest time to complete.
Correct Answer:
Verified
Q46: Short- to medium-term project selection with predictable
Q47: If we cannot estimate probabilities because the
Q48: Which of the following is not a
Q49: Popular techniques to plan for and monitor
Q50: Activity times for a project can be
Q52: A project has three possible paths from
Q53: Given that activity B has the following
Q54: Which of the following is the critical
Q55: What is the project duration for the
Q56: Using the information shown in the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents