Question 41
Multiple Choice
Project management involves managing all of the following except
Question 42
Multiple Choice
Project performance can be assessed by measuring all of the following dimensions except
Question 43
Multiple Choice
Which of the following is not a phase of a project?
Question 44
Multiple Choice
An organizational structure where team members are assigned to a project and report directly to the project manager is called
Question 45
Multiple Choice
The "dual-boss" problem occurs in a
Question 46
Multiple Choice
Short- to medium-term project selection with predictable cash flows can be done by which of the following methods?
Question 47
Multiple Choice
If we cannot estimate probabilities because the project cash flows are uncertain, then we can use all of the following methods except
Question 48
Multiple Choice
Which of the following is not a method used to evaluate projects with unpredictable cash flows where probabilities cannot be estimated?
Question 49
Multiple Choice
Popular techniques to plan for and monitor a project include
Question 50
Multiple Choice
Activity times for a project can be estimated by all but which of the following methods?
Question 51
Multiple Choice
Which one of the following statements best describes the critical path of a project network?
Question 52
Multiple Choice
A project has three possible paths from start to finish. Path A-B-C is 15 hours; path A-C-D is 10 hours, and path A-C-E is 20 hours. Which one of the following statements is true?
Question 53
Multiple Choice
Given that activity B has the following times, which of the following statements is true about activity B? Earliest start time = 9 days; latest start time = 17 days; earliest finish time = 15 days; latest finish time = 23 days