Services
Discover
Homeschooling
Ask a Question
Log in
Sign up
Filters
Done
Question type:
Essay
Multiple Choice
Short Answer
True False
Matching
Topic
Business
Study Set
An Introduction to Operations Management
Quiz 13: Working With Projects
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Practice Exam
Learn
Question 61
Multiple Choice
Using the information shown in the following table, the expected time for activity B is
Question 62
Multiple Choice
Using the information shown in the previous table, what is the variance for activity H?
Question 63
Multiple Choice
Using the information shown in the previous table, what is the standard deviation for the entire project?
Question 64
Multiple Choice
If the length of the critical path is 25 weeks, what is the probability that the project will be completed on or before 22 weeks?
Question 65
Multiple Choice
If the length of the critical path is 25 weeks, what is the shortest project due date if the project manager wants at least a 98 percent probability that the project will be completed on or before the due date?
Question 66
Multiple Choice
Using the data supplied in the following table, by how many weeks can we crash activity A?
 ActivityÂ
 NormalÂ
 TimeÂ
 CrashÂ
 TimeÂ
 NormalÂ
 CostÂ
 CrashÂ
 CostÂ
 Availab leÂ
 Weeks ofÂ
 CrashingÂ
 CrashingÂ
 Cost/WeekÂ
 AÂ
4
2
$
15
,
000
$
21
,
000
 BÂ
3
2
$
15
,
000
$
18
,
000
 CÂ
4
4
$
9
,
000
$
9
,
000
D
5
3
$
10
,
000
$
16
,
000
E
4
1
$
10
,
000
$
13
,
000
 FÂ
1
1
$
10
,
000
$
10
,
000
\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Normal } \\\text { Time }\end{array} & \begin{array} { c } \text { Crash } \\\text { Time }\end{array} & \begin{array} { c } \text { Normal } \\\text { Cost }\end{array} & \begin{array} { c } \text { Crash } \\\text { Cost }\end{array} & \begin{array} { c } \text { Availab le } \\\text { Weeks of } \\\text { Crashing }\end{array} & \begin{array} { c } \text { Crashing } \\\text { Cost/Week }\end{array} \\\hline \text { A } & 4 & 2 & \$ 15,000 & \$ 21,000 & & \\\hline \text { B } & 3 & 2 & \$ 15,000 & \$ 18,000 & & \\\hline \text { C } & 4 & 4 & \$ 9,000 & \$ 9,000 & & \\\hline \mathrm { D } & 5 & 3 & \$ 10,000 & \$ 16,000 & & \\\hline E & 4 & 1 & \$ 10,000 & \$ 13,000 & & \\\hline \text { F } & 1 & 1 & \$ 10,000 & \$ 10,000 & & \\\hline\end{array}
 ActivityÂ
 AÂ
 BÂ
 CÂ
D
E
 FÂ
​
 NormalÂ
 TimeÂ
​
4
3
4
5
4
1
​
 CrashÂ
 TimeÂ
​
2
2
4
3
1
1
​
 NormalÂ
 CostÂ
​
$15
,
000
$15
,
000
$9
,
000
$10
,
000
$10
,
000
$10
,
000
​
 CrashÂ
 CostÂ
​
$21
,
000
$18
,
000
$9
,
000
$16
,
000
$13
,
000
$10
,
000
​
 Availab leÂ
 Weeks ofÂ
 CrashingÂ
​
​
 CrashingÂ
 Cost/WeekÂ
​
​
​
Question 67
Multiple Choice
Using the data supplied, what is the crashing cost per week for activity A?
Question 68
Multiple Choice
Using the data supplied, if a decision is made to crash activity C, what is the cost for this one week of crashing?
Question 69
Multiple Choice
Using the data supplied, which activity should be crashed first if the critical path is A-B-D-E?
Question 70
Multiple Choice
If activity E is reduced by 1 week and activity A is reduced by 2 weeks, what is the new total project cost?
Question 71
Short Answer
A(n) __________ has specific goals, linked work steps with a specified timeline, a clear start and finish, and is fairly unique and nonrepetitive.
Question 72
Short Answer
__________ is the art of orchestrating time and resources to meet and manage stakeholder goals, project risks, and project changes.
Question 73
Short Answer
Managing multiple projects is called __________.
Question 74
Short Answer
Project performance has three dimensions: __________, __________, and __________.
Question 75
Short Answer
The __________ phase is when project details are thrashed out and documented.
Question 76
Short Answer
Lucy, the project manager, and her team were able to archive important project documents in a safe and accessible place and then celebrate during the __________ phase of the project.
Question 77
Short Answer
Larry was part of a project team due to his technical expertise. However, he was faced with the dilemma of reporting to two bosses: one in his functional area and his project manager. Larry is in a firm that has a(n) __________ organizational structure.
Question 78
Short Answer
__________ and __________ are two methods of evaluating short- to medium-term projects with predictable cash flows.
Question 79
Short Answer
Janet was tasked with assessing competing projects with unpredictable cash flows and where the probabilities could not be estimated. In order for her to perform her analysis, she should use the __________ or __________ techniques.