Which of the following statements is not true?
A) Discrepancies between activity levels in the static budget and actual activity levels result in expense variances that are not necessarily reflective of performance.
B) Flexible budgeting can be achieved by preparing a series of budgets for different levels of sales activity.
C) Any unfavourable cost variances between actual performance and the flexible budget will be attributable to inefficient use of resources.
D) A flexible budget will show what costs and revenues should have been for the actual level of activity achieved.
E) When preparing a flexible budget, changes are generally not made to fixed costs to reflect updated information available.
Correct Answer:
Verified
Q1: A flexible budget:
A) Refers to a budget
Q3: Use the following information to answer the
Q4: Use the following information to answer the
Q5: Use the following information to answer the
Q6: Use the following information to answer the
Q7: The term 'benchmarking' is generally used to
Q8: A materials price variance can be calculated
Q9: A materials efficiency variance can be calculated
Q10: A labour rate variance can be calculated
Q11: Use the following information to answer the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents