It was Bob's job to figure out the dependencies among the schedule activities. Bob discovered that all these dependencies are of type finish-to-start. Now Bob needs a network diagramming method to display these dependencies. Which should he use?
A) Arrow diagramming method only
B) Precedence diagramming method only
C) Either the PDM or the ADM
D) Critical diagramming method
Correct Answer:
Verified
Q64: A resource histogram is used in which
Q65: Josh is working on a brand new
Q66: The schedule management plan is an output
Q67: The Black Forest Tie Affair program is
Q68: David is the program manager of the
Q70: In order to determine the program budget,
Q71: Boris is the manager of the Yes
Q72: From which of the following do risks
Q73: Which is NOT included in the Communication
Q74: What is needed before performing the Quality
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents