Question 61
Multiple Choice
The Scope Definition process generates which of the following:
Question 62
Multiple Choice
What are the components at the lowest level of a program WBS hierarchy called?
Question 63
Multiple Choice
Dixon is performing the Interface Planning process for his Art-2 Unit program. Which is not a tool or technique that can be used for this process?
Question 64
Multiple Choice
A resource histogram is used in which process?
Question 65
Multiple Choice
Josh is working on a brand new program, Need a Date!, and he's going to be performing the following processes for the first time for his program. Which is the first process he should perform?
Question 66
Multiple Choice
The schedule management plan is an output of which of the following processes?
Question 67
Multiple Choice
The Black Forest Tie Affair program is currently in the planning stages. Its program sponsor, Randolph Moneypenny, says to Miguel, the program manager, "I need an organizational chart. Please perform this process." Which process is Mr. Moneypenny speaking of?
Question 68
Multiple Choice
David is the program manager of the Make It Look Good program, which is in the planning stage. David isn't certain if items should be purchased or produced in-house. Which process should David perform to decide?
Question 69
Multiple Choice
It was Bob's job to figure out the dependencies among the schedule activities. Bob discovered that all these dependencies are of type finish-to-start. Now Bob needs a network diagramming method to display these dependencies. Which should he use?
Question 70
Multiple Choice
In order to determine the program budget, which program management process must be performed?
Question 71
Multiple Choice
Boris is the manager of the Yes I Read book-publishing program. He has decided to procure book cover images from a digital design company for the next fiscal year. Currently Boris has no idea how many books he will publish in the year. What type of contract is most suitable for Boris to use when he signs with the digital design company?
Question 72
Multiple Choice
From which of the following do risks originate?
Question 73
Multiple Choice
Which is NOT included in the Communication Planning process?
Question 74
Multiple Choice
What is needed before performing the Quality Planning process?
Question 75
Multiple Choice
What are the two main types of project reserve accounts? Select two:
Question 76
Multiple Choice
Which statement is correct?
Question 77
Multiple Choice
What is a risk response plan for a program an output of?
Question 78
Multiple Choice
Which process must be performed to develop a contract statement of work?
Question 79
Multiple Choice
Boris wants to figure out how much more his company should invest into the quality of a certain product. What tool would be most effective for this exercise?
Question 80
Multiple Choice
Boris hires an outside vendor to maintain their servers. However, he is extremely concerned about uptime. In order to remain profitable, Boris' company needs to have 99% uptime. Which of the following would be a clause Boris would want to include in the contract to directly address this requirement?