Jack is concerned about slack. His project at the corporate offices of Taco Shack is catching flack, because it might be off track, and impact his delivery date. Given that, which type of slack best represents the above?
A) Near critical path float
B) Total float
C) Project float
D) Free float
Correct Answer:
Verified