Once the Project Manager completes the schedule network analysis, the risk that is identified must be cared for within the project schedule. What type of formats are permissible ways to show logical relationships?
A) Network Diagram
B) Project Scope Statement
C) Progress Reports
D) Critical Path Baseline
E) PERT
Correct Answer:
Verified