Identifying a plan's critical path allows the Project Manager to monitor the activities that:
1) Must be completed on time if the whole plan is to be finished on schedule
2) Can be omitted if time tolerances are exceeded
3) Are not allowed any time tolerance
4) Can be delayed for a while if resources become tight
A) 1, 2
B) 2, 3
C) 1, 4
D) 3, 4
Correct Answer:
Verified
Q49: Which of the following statements is true?
A)Management
Q50: The Project Brief is assembled in which
Q51: Which of the following roles must be
Q52: Which role is responsible for committing supplier
Q53: What are the two types of progress
Q55: Which role is responsible for defining the
Q56: At what point is a Stage Plan
Q57: There are at least how many valid
Q58: Which of the true is following about
Q59: Product Descriptions are contained within which other
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents