Question 41
Multiple Choice
Which process can be carried out without using PRINCE2?
Question 42
Multiple Choice
Which of the following is part of the PRINCE2 product based planning approach?
Question 43
Multiple Choice
During which process is a Checkpoint Report produced?
Question 44
Multiple Choice
Which PRINCE2 theme is one of the few to provide techniques?
Question 45
Multiple Choice
Which of the following are valid responses to a Request for Change? 1) Approve the change 2) Defer decision 3) Increase the tolerances 4) Ask for an exception plan
Question 46
Multiple Choice
Is it possible to change a Product Description once it has been approved?
Question 47
Multiple Choice
To which section of the Quality Management Strategy does the assignment of the Project Manager role belong?
Question 48
Multiple Choice
As part of which process are decisions made regarding stage tolerance exceptions?
Question 49
Multiple Choice
Which of the following statements is true?
Question 50
Multiple Choice
The Project Brief is assembled in which process?
Question 51
Multiple Choice
Which of the following roles must be mutually exclusive according to PRINCE2? 1) Executive 2) Project Manager 3) Project Assurance 4) Project Support
Question 52
Multiple Choice
Which role is responsible for committing supplier resources to the Stage Plans?
Question 53
Multiple Choice
What are the two types of progress controls provided by PRINCE2? 1) Stage-driven 2) Tolerance-driven 3) Time-driven 4) Event-driven
Question 54
Multiple Choice
Identifying a plan's critical path allows the Project Manager to monitor the activities that: 1) Must be completed on time if the whole plan is to be finished on schedule 2) Can be omitted if time tolerances are exceeded 3) Are not allowed any time tolerance 4) Can be delayed for a while if resources become tight
Question 55
Multiple Choice
Which role is responsible for defining the role descriptions within the project?
Question 56
Multiple Choice
At what point is a Stage Plan updated with actuals?
Question 57
Multiple Choice
There are at least how many valid business cases within the commercial context of any project?
Question 58
Multiple Choice
Which of the true is following about projects? 1) They are driven by deliverables 2) They have finite timescales 3) They involve changes to the business capability 4) They have benefits that are usually realized after project closure
Question 59
Multiple Choice
Product Descriptions are contained within which other product?
Question 60
Multiple Choice
The Product Description includes: 1) Composition 2) Format and Presentation 3) Quality Responsibilities 4) Item Attributes