Which of the following best describes the scheduling term float?
A) Amount of time spent on a specific task
B) Time to complete a specific task that is dependent on a preceding task
C) Amount of time a task can be delayed without impacting a subsequent task or project completion date
D) None of the above
Correct Answer:
Verified
Q2: What critical path project management tool is
Q3: Which of the following best describes the
Q4: Which of the following project management tools
Q5: Which of the following project management tools
Q6: Using the three-point estimate technique, what is
Q7: Which of the following best describes the
Q8: Which of the following terms is used
Q9: Which of the following project management tools
Q10: Which of the following is a basic
Q11: Using the three-point estimate technique, what is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents