Pick up the correct statement from the following:
A) the earth work of cutting in trenches or borrow pits in fairly uniform ground is measured with the help of average depths of the dead men
B) the earth work in trenches or borrow pits in irregular ground is measured by taking the difference in levels before and after completion of work
C) the earth work in trenches or borrow pits, where neither a nor b is feasible, are measured from the fillings after deduction of voids
D) all the above
Correct Answer:
Verified
Q7: A cement concrete road is 1000 m
Q8: While estimating the qualities for the construction
Q9: The brick work is not measured in
Q10: The assumption on which the trapezoidal formula
Q11: In the mid-section formula
A)the mean depth is
Q13: The cross-sections for a highway is taken
Q14: Referring of given figure, pick up the
Q15: According to Indian Standards Institute, the actual
Q16: The following item of earth work is
Q17: The measurement is made in square metre
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents