The following item of earth work is not measured separately.
A) setting out of works
B) site clearance
C) steps in deep excavation
D) all the above
Correct Answer:
Verified
Q11: In the mid-section formula
A)the mean depth is
Q12: Pick up the correct statement from the
Q13: The cross-sections for a highway is taken
Q14: Referring of given figure, pick up the
Q15: According to Indian Standards Institute, the actual
Q17: The measurement is made in square metre
Q18: Cost of fittings and their fixing is
Q19: The excavation exceeding 1.5 m in width
Q20: For the construction of buildings, the subheads
Q21: Pick up the correct statement from the