Liquidated damages clauses __________ be enforced if the amount is unreasonably high and functions as a penalty.
A) may
B) will not
C) will
D) can
Correct Answer:
Verified
Q29: T.T. Inc. creates and sells hats. The
Q30: T.T. Inc. creates and sells hats. The
Q31: The UCC provides the buyer with an
Q32: A contractual remedy in which the court
Q33: A buyer may incur incidental and _
Q34: _ damages are damages that the parties
Q35: The parties _ add a liquidated damages
Q37: Liquidated damages that are unreasonably low will
Q38: There are four critical dates that impact
Q39: T.T. Inc. creates and sells hats. The