Miley, Inc. began work in 2008 on a contract for $8,400,000. Other data are as follows:
-If Miley uses the percentage-of-completion method, the gross profit to be recognized in 2008 is
A) $1,440,000.
B) $1,600,000.
C) $2,160,000.
D) $2,400,000.