Before Any Lumber Is Sent to a Construction Site, Contractor

Question 110

Multiple Choice

Before any lumber is sent to a construction site, contractor Jack Smith inspects every truckload of wood for defects and quality. This preventive control step can best be described as which of the following?


A) concurrent control.
B) feedforward control.
C) cross-functional control
D) safeguarding control
E) feedforward control