The standard rate for direct labor was established at $15 per hour at the beginning of the year at Rodriguez Inc. In September a new labor contract was negotiated that raised the rate to $18.50 per hour. Mr. Garcia, the controller, decided not to change the standard rate since the end of the year was relatively close and new standards would be developed, effective January 1.
During October 16,000 labor hours were used at an average cost of $19 per hour. The labor rate variance was $64,000 unfavorable. The production manager was understandably upset by this variance and wanted an explanation from Mr. Garcia.
Required:
(1) Assume you are Mr. Garcia. Explain to the production manager why the unfavorable rate variance was so high.
(2) In general, can variances be analyzed to separate out items that cannot be controlled from those that can be?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q70: What are some of the advantages and
Q71: The records for March showed the following
Q72: Actual results for September were:
Q73: During May, the following actual activities occurred:
Q74: Yield 63,000 units Required:
(1) Calculate the material
Q75: Yield 96,600 units Required:
(1) Calculate the material
Q76: The following actual production information was recorded
Q77: Mercury Company is meeting with the consultants
Q78: Coiller Company uses a standard cost system
Q79: Az Company currently uses a traditional standard
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents