Indicating when and how written and oral reports will be provided by the team, how team members will coordinate work, what messages will be sent to announce the project to interested parties, and what kinds of information will be shared with vendors and external contractors involved with the project describes:
A) determining project standards and procedures.
B) developing a project scope statement.
C) developing a communication plan.
D) setting a baseline project plan.
E) establishing the project initiation team.
Correct Answer:
Verified
Q70: Which of the following occurs during project
Q71: Pessimistic time refers to:
A) the maximum period
Q72: Which of the following states correctly the
Q73: Determining the strengths and weaknesses of project
Q74: Optimistic time refers to:
A) the maximum period
Q76: Any person, group of people, piece of
Q77: The final phase of the project management
Q78: Risks can arise from:
A) the use of
Q79: A scheduling technique where the order and
Q80: A technique that uses optimistic, pessimistic, and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents