Pessimistic time refers to:
A) the maximum period of time for an activity to be completed.
B) the minimum period of time for an activity to be completed.
C) the planner's "best guess" of the amount of time the activity actually will require for completion.
D) the maximum period of time for an entire project to be completed.
E) the average period of time for an activity to be completed.
Correct Answer:
Verified
Q66: The responsibility for keeping all team members
Q67: A critical path refers to:
A) a sequence
Q68: Realistic time refers to:
A) the maximum period
Q69: What would be the estimated time for
Q70: Which of the following occurs during project
Q72: Which of the following states correctly the
Q73: Determining the strengths and weaknesses of project
Q74: Optimistic time refers to:
A) the maximum period
Q75: Indicating when and how written and oral
Q76: Any person, group of people, piece of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents