A defense contractor has just started producing turbines for a new government contract. The first turbine took 7000 hours to produce. If the learning curve is 90%, how long will it take to produce the 10th turbine? (Use at least three decimals in the exponent if you use the logarithmic approach.)
A) less than 4800 hours
B) from 4800 to 4900 hours
C) from 4900 to 5000 hours
D) from 5000 to 5100 hours
E) over 5100 hours
Correct Answer:
Verified
Q2: A job with a 90% learning curve
Q41: The first unit of a product took
Q42: The first product took 10 hours to
Q43: The first unit of a product took
Q44: The first unit of a product took
Q48: Suppose that there are two products with
Q49: It took 60 hours to make the
Q50: The first unit took 10 hours and
Q50: The first unit took 10 hours and
Q53: The first unit took 10 hours and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents