A Defense Contractor Has Just Started Producing Turbines for a New

Question 45

Multiple Choice

A defense contractor has just started producing turbines for a new government contract. The first turbine took 7000 hours to produce. If the learning curve is 90%, how long will it take to produce the 10th turbine? (Use at least three decimals in the exponent if you use the logarithmic approach.)


A) less than 4800 hours
B) from 4800 to 4900 hours
C) from 4900 to 5000 hours
D) from 5000 to 5100 hours
E) over 5100 hours