In MRP record calculations, the appearance of a negative value for the gross requirements of an end item in a specific time bucket
A) signals the need to purchase that end item in that period
B) implies that value was scheduled by the MPS
C) signals the need for a negative planned order receipt in that period
D) is impossible
E) All of the above are true.
Correct Answer:
Verified
Q70: Linking a part requirement with the parent
Q71: Given the following bill of material
Q72: Each R requires 2 of component S
Q73: The MPS calls for 50 units of
Q74: Given the following bill of material
Q76: The minimum record accuracy required for successful
Q77: Low level coding means that
A) a final
Q78: Each X requires 2 of component Y;
Q79: In MRP, the number of units projected
Q80: The MPS calls for 110 units of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents