Linking a part requirement with the parent component that caused the requirement is referred to as
A) net requirements planning
B) a time fence
C) pegging
D) kanban
E) leveling
Correct Answer:
Verified
Q56: Which of the following best describes a
Q65: When safety stock is deemed absolutely necessary,
Q66: Each R requires 4 of component S;
Q67: Given the following bill of material
Q69: If safety stock is desired it should
Q71: Given the following bill of material
Q72: Each R requires 2 of component S
Q73: The MPS calls for 50 units of
Q74: Given the following bill of material
Q75: In MRP record calculations, the appearance of