Which of the following statements is true about the MRP plan when using lot-for-lot ordering?
A) The quantity of gross requirements for a child item is always equal to the quantity of planned order releases for its parent.
B) The quantity of gross requirements for a child item is equal to the quantity of planned order release(s) multiplied by the number of child items used in the parent assembly.
C) The quantity of gross requirements for a child item is always equal to the quantity of gross requirements for its parent.
D) The quantity and gross requirements for a child item is always equal to the quantity of net requirements for its parent.
E) All of the above are true.
Correct Answer:
Verified
Q74: Distortion in MRP systems can be minimized
Q84: Capacity planning in closed-loop MRP:
A)utilizes feedback about
Q91: Which of the following is a step
Q92: The extension of MRP which extends to
Q94: For the lot-sizing technique known as lot-for-lot
Q95: Which of the following lot-sizing techniques results
Q97: What lot-sizing technique is generally preferred when
Q98: A firm makes numerous models of mowers,
Q111: If a load report (resource requirements profile)
Q118: A(n) _ provides feedback to the capacity
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents