Which of the following statements regarding MRP in services is true?
A) MRP is for manufacturing only, and is not applicable to services.
B) MRP can be used in services, but only those that offer very limited customization.
C) MRP does not work in services because there is no dependent demand.
D) Services such as restaurant meals illustrate dependent demand, and require product structure trees, bills-of-material, and scheduling.
E) None of the above is true.
Correct Answer:
Verified
Q67: In MRP, system nervousness is caused by:
A)
Q86: MRP II is accurately described as
A) MRP
Q87: Distribution resource planning (DRP) is
A) a transportation
Q88: Which of the following statements regarding lot-sizing
Q89: Which of the following best differentiates material
Q91: Which of the following is a step
Q92: The extension of MRP which extends to
Q94: For the lot-sizing technique known as lot-for-lot
Q95: Which of the following lot-sizing techniques results
Q111: If a load report (resource requirements profile)
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents