The MPS calls for 50 units of Product A and 60 of B. There are currently 35 of Product B on hand. Each A requires 2 of Part C; each B requires 5 of C. There are 160 units of C available.
a. Calculate the net requirements for B.
b. Calculate the gross requirements for C.
c. Calculate the net requirements for C.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q75: Product A is made from 2 Bs
Q113: What do we mean by closed-loop MRP?
Q129: What is DRP?
Q154: What types of resources might be scheduled
Q155: What are the disadvantages of enterprise resource
Q156: Consider the following bill of material. Fifty
Q160: Identify the several lot-sizing algorithms used in
Q161: Each X requires 2 of component Y
Q163: A company is trying to implement MRP
Q164: Explode the following Bill of materials assuming
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents