Each X requires 2 of component Y and 1 of part W. Each Y requires 10 of Z. Each W requires 3 of Q and 2 of R. Lead times are X = 1 week, Y = 1 week, W = 2 weeks, R = 1 week, Z = 3 weeks, and Q = 3 weeks.
a. Construct the time-phased product structure.
b. Construct the bill of material.
Correct Answer:
Verified
Q75: Product A is made from 2 Bs
Q113: What do we mean by closed-loop MRP?
Q129: What is DRP?
Q156: Consider the following bill of material. Fifty
Q159: The MPS calls for 50 units of
Q160: Identify the several lot-sizing algorithms used in
Q163: A company is trying to implement MRP
Q164: Explode the following Bill of materials assuming
Q165: Construct an indented bill of material for
Q166: Each R requires 3 of component S