
Consider the following work breakdown structure:
What is the estimated expected (mean) time for activity E?
A) 35 days
B) 36 days
C) 39 days
D) 40 days
E) 45 days
Correct Answer:
Verified
Q80: In the probabilistic approach to project network
Q81: Consider the following work breakdown structure:
Q82: A project is represented by the following
Q83: Consider the following work breakdown structure:
Q84: Consider the following work breakdown structure:
Q86: Consider the following work breakdown structure:
Q87: Consider the following work breakdown structure:
Q88: A project is represented by the following
Q89: Consider the following work breakdown structure:
Q90: Consider the following work breakdown structure:
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents