Question 1
True/False
The project sponsor and project champion should be the same person on any project.
Question 2
True/False
The goal of the activity definition process is to replace the scope statement.
Question 3
True/False
The contents of scope statements can vary.
Question 4
True/False
The project management plan typically provides detailed cost projections by WBS by month.
Question 5
True/False
The tasks in a WBS must be developed as a sequential list of steps.
Question 6
True/False
People are more likely to perform well if they know what they are supposed to do and when.
Question 7
True/False
The project team should review an activity list and activity attributes with project stakeholders.
Question 8
True/False
As more information becomes available and decisions are made related to project scope,the project team should update the project scope statement.
Question 9
True/False
The WBS is a peripheral document in project management.
Question 10
True/False
Discretionary dependencies are defined by the project team.
Question 11
True/False
Specifications on a WBS represent work that needs to be done to complete the project.
Question 12
True/False
The project manager monitors and controls work packages at the lowest level of the WBS.
Question 13
True/False
You need a detailed project schedule before you can develop a cost baseline.
Question 14
True/False
Activity sequencing involves reviewing the activity list and attributes,project scope statement,and milestone list to determine the relationships or dependencies between activities.