Under the Triple Constraints of Project Management, Which of the Following

Question 15

Multiple Choice

Under the triple constraints of project management, which of the following is not a correct statement?


A) Cost and/or time can often be saved by increasing scope.
B) Scope can often be increased by using additional time and incurring increased costs
C) Cost and/or time can often be saved by reducing scope.
D) For a given scope, time can sometimes be saved by increasing cost.