Considering the Knowledge Areas of PMBOK, This One Includes Those

Question 19

Multiple Choice

Considering the knowledge areas of PMBOK, this one includes those processes that are required to ensure that all the project's components are properly coordinated.


A) Project Time Management
B) Project Integration Management
C) Project Quality Management
D) Project Risk Management

Correct Answer: