The largest value of EF and LF at the last node in the network is the
A) backward pass point of the project.
B) project completion time.
C) time-length of the critical path.
D) all of the above
Correct Answer:
Verified
Q74: Every event node in the PERT network
Q75: Which of the following selections is the
Q76: Which choice translates to allowable slippage in
Q77: _ is when each activity will be
Q78: If you are going to crash one
Q80: Which of the following is the first
Q81: The earliest start for each beginning node
Q82: When activities are represented as arrows,then the
Q83: How was PERT developed and what was
Q84: Resource leveling:
A)shifts costs among activities.
B)does not add