Which choice translates to allowable slippage in an activity's schedule along a slack path?
A) LS - ES > 0
B) LF - EF > 0
C) Slack > 0
D) all of the above
Correct Answer:
Verified
Q71: Project redesign is often used to _.
A)meet
Q72: In general,the most important dimension for evaluating
Q73: When using the equation Estimate - Actual
Q74: Every event node in the PERT network
Q75: Which of the following selections is the
Q77: _ is when each activity will be
Q78: If you are going to crash one
Q79: The largest value of EF and LF
Q80: Which of the following is the first
Q81: The earliest start for each beginning node