Which of the following types of dependencies are inherent in the nature of work being performed on a project?
A) Mandatory
B) Discretionary
C) External
D) Random
Correct Answer:
Verified
Q44: After working with key stakeholders to define
Q45: Which of the following is a network
Q46: In project time management, the ultimate goal
Q47: _ is the amount of time an
Q48: A(n) _ on a project is a
Q50: AOA network diagrams use only _ dependencies.
A)start-to-start
B)finish-to-start
Q51: In project time management, the next step
Q52: A network diagramming technique in which boxes
Q53: Which of the following is a relationship
Q54: Which of the following is true of