Which of the following is a network diagramming technique used primarily to predict total project duration?
A) Gantt chart
B) Critical path analysis
C) Resource breakdown structure
D) Arrow diagramming method
Correct Answer:
Verified
Q40: In project time management, the process of_
Q41: _ dependencies are sometimes referred to as
Q42: Which of the following is one of
Q43: In project time management, the main goal
Q44: After working with key stakeholders to define
Q46: In project time management, the ultimate goal
Q47: _ is the amount of time an
Q48: A(n) _ on a project is a
Q49: Which of the following types of dependencies
Q50: AOA network diagrams use only _ dependencies.
A)start-to-start
B)finish-to-start