A similarity between the crashing technique and the fast tracking technique is that:
A) both spread out tasks over a long period of time to ensure the quality of work is maintained.
B) both invariably result in increases in total project costs.
C) both can shorten the time needed to finish a project.
D) both are network diagramming techniques used primarily to predict total project duration.
Correct Answer:
Verified
Q62: _ involves the processes required to ensure
Q64: In project time management, the process of
Q65: _ states that work expands to fill
Q66: Which of the following techniques involve doing
Q67: Which of the following is an output
Q68: Critical chain scheduling protects tasks on the
Q70: In project procurement management, which of the
Q73: Which of the following is a silimarity
Q74: The _ is a tabulation of activities
Q80: In a project schedule, the variable that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents