Critical Chain Scheduling Protects Tasks on the Critical Chain from Being

Question 68

Multiple Choice

Critical chain scheduling protects tasks on the critical chain from being delayed by using _____, which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks.


A) critical paths
B) feeding buffers  
C) dummy activities
D) fast tracking

Correct Answer: