Critical chain scheduling protects tasks on the critical chain from being delayed by using _____, which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks.
A) critical paths
B) feeding buffers
C) dummy activities
D) fast tracking
Correct Answer:
Verified
Q62: _ involves the processes required to ensure
Q63: The technique for making cost and schedule
Q64: In project time management, the process of
Q65: _ states that work expands to fill
Q66: Which of the following techniques involve doing
Q67: Which of the following is an output
Q69: A similarity between the crashing technique and
Q70: In project procurement management, which of the
Q73: Which of the following is a silimarity
Q74: The _ is a tabulation of activities