Which of the following is the longest path of the network,determines the total duration of the project,and is also the shortest amount of time necessary to accomplish the project?
A) burst path
B) critical path
C) project path
D) designated path
Correct Answer:
Verified
Q40: Which of the following demands extensive hardware,is
Q41: Advantages of PERT include
A)inexpensive to maintain.
B)flexibility.
C)easy to
Q42: For an activity,assume the early start is
Q43: PDM is useful because it provides
A)the start
Q44: Causing a delay to the whole project
Q46: Negative slack can occur due to
A)unavailability of
Q47: For an activity,assume the early start is
Q48: Causing a delay to a subsequent activity
Q49: Which of the following is used in
Q50: When constructing the PDM,an activity can have
A)predecessors
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents