Which of the following is used in project planning because it helps a project manager to identify interdependencies and problems between various activities?
A) QFD
B) TMAP
C) PERT
D) SWOT
Correct Answer:
Verified
Q44: Causing a delay to the whole project
Q45: Which of the following is the longest
Q46: Negative slack can occur due to
A)unavailability of
Q47: For an activity,assume the early start is
Q48: Causing a delay to a subsequent activity
Q50: When constructing the PDM,an activity can have
A)predecessors
Q51: Which of the following usually occurs when
Q52: A specific task,or set of tasks,that is
Q53: When working with project management software,factors that
Q54: The shortest time in which an activity
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents