When working with project management software,factors that drive the calculation of time include each of the following except
A) resource assignments and types.
B) task dependencies.
C) task iterations.
D) project calendars.
Correct Answer:
Verified
Q48: Causing a delay to a subsequent activity
Q49: Which of the following is used in
Q50: When constructing the PDM,an activity can have
A)predecessors
Q51: Which of the following usually occurs when
Q52: A specific task,or set of tasks,that is
Q54: The shortest time in which an activity
Q55: Which of the following is used to
Q56: Dependencies defined by the project team are
A)discretionary
Q57: The amount of time that an activity
Q58: Basic reasons for creating dependencies of project