A specific task,or set of tasks,that is part of the scope of a project,uses up some of the resources of a project,and requires some finite time to be completed best defines
A) activity.
B) deliverable.
C) SWOT summary.
D) product.
Correct Answer:
Verified
Q47: For an activity,assume the early start is
Q48: Causing a delay to a subsequent activity
Q49: Which of the following is used in
Q50: When constructing the PDM,an activity can have
A)predecessors
Q51: Which of the following usually occurs when
Q53: When working with project management software,factors that
Q54: The shortest time in which an activity
Q55: Which of the following is used to
Q56: Dependencies defined by the project team are
A)discretionary
Q57: The amount of time that an activity